A downtown Miami block next to the Knight Center Metromover station could get 1,344 new homes.

Namdar Group wants to replace the Ultramont Mall at 101 SE 1st Ave. with two 42-story towers holding 1,344 homes, according to its filing with the city. The plan goes before Miami's Urban Development Review Board on Wednesday. So do a 76-story tower in Brickell and a 43-story tower on the Edgewater bayfront. Together, the three plans add up to 2,109 homes.

Namdar 101: 1,344 homes downtown

The Namdar towers, designed by Behar Font & Partners, would rise about 436 feet over a shared base, Florida YIMBY reported. They would go up in two phases. The north tower, at 100 SE 1st St., comes first. The south tower, at 101 SE 2nd St., follows.

Most would be studios and one-bedrooms. The plans list 398 studios, 802 one-bedrooms and 144 two-bedrooms. The base would hold 287 parking spaces, 1,347 bike spaces and 7,832 square feet of shops. Amenities include pools, a pickleball court, coworking space and a golf room.

The site is inside the Downtown Miami Historic Commercial District, but the application lists it as a non-contributing property. The plans say the project does not use Florida's Live Local Act, the state law that lets developers skip some local zoning limits.

B Residences: 834 feet in Brickell

At 11 SW 7th St., just north of Brickell City Centre, Empira Group and Partners Group plan B Residences Miami, a Breitling-branded tower designed by Arquitectonica. The application describes a 76-story building, 834 feet tall, with 369 homes and 707 parking spaces, Florida YIMBY reported. Plans show about 14,800 square feet of ground-floor retail. The site is mostly surface parking today.

The developer is asking for one waiver under the city's zoning code, to put parking on the second floor along the street side of the building behind an art and glass screen. When the project was announced in June, construction was expected to start in late 2028, with completion targeted for 2031.

Edgewater: 396 homes on the bay

The third tower would rise 43 stories at 720 NE 27th St., on Biscayne Bay between NE 27th Street and NE 26th Terrace. The filing lists 396 homes, 591 parking spaces and 1,800 square feet of commercial space on a 1.49-acre site. Arquitectonica is the architect, and the buildings on the site now would be torn down.

Thirty-two of those homes come from a payment into the city's Edgewater Resilience Trust Fund, and under city code those units don't need parking, the filing says. Cain and Kushner announced in April that they would build an apartment tower on the site, Bisnow reported. At the time, they described 40 stories and 364 units.

What happens next

The review board votes on whether to recommend each project. Its recommendation goes to the planning director, who decides whether to approve the site plans. No construction can start until the city issues building permits.

The same board recently backed the Edgewater church tower at 1836 Biscayne and Magic City's 553 rentals in Little Haiti. In Brickell, the tower pipeline also includes the 1,049-foot ATMA plan on Brickell Bay Drive.

Buying or selling in Downtown Miami? The Miami Lookout is founded by Joe Biscaha, a Miami real estate advisor with Compass.

The Ultramont Mall in downtown Miami in 2022